Estimation: human days vs AI-agent days

Generated on 2026-10-27 from the backlog in the GitHub Project (97 stories, 23 epics, 15 repositories). Re-run after the first 15 stories with measured data.

Summary

Optimistic Likely Pessimistic
Ideal engineering days (sum of PERT estimates) 146 146 146
Human person-days (with review, tests, docs, integration) 193 218 264
Human team of 3, calendar 17 weeks 22 weeks 32 weeks
One human alone, calendar 51 weeks 67 weeks 96 weeks
AI agent compute (4 agents, hours of agent work) 134 h 325 h 616 h
Human supervision (specs, reviews, takeovers, design) 678 h 1,134 h 2,317 h
Supervision as share of human effort 44% 65% 110%
AI team calendar, part-time maintainer (15 h/week + 4 agents) 45 weeks 76 weeks 154 weeks
AI team calendar, full-time supervisor (30 h/week + 4 agents) 23 weeks 38 weeks 77 weeks

How to read it - "Human days" = what a team of experienced developers would spend, everything included. - "AI days" has two parts: agent compute is cheap and fast (about 32 agent-days of 10 h); the human supervising is the bottleneck (about 189 days of 6 productive hours). - With one full-time supervisor, agents finish in about 38 weeks what one human alone would do in 67 weeks (1.8x faster), but a team of three humans is still faster on the calendar (22 weeks). - The part-time scenario is the roadmap's basis: it is honest about evenings and weekends.

Where the supervision goes (likely)

Risk class Stories Human days Supervision hours Supervision / human effort
Security 16 42.1 295 88%
Normal 35 64.3 128 25%
External API 8 19.4 100 64%
Core contract 9 22.8 66 36%
Integration 6 12.9 52 50%
Human-only 7 6.3 39 77%
Design/prompt 5 8.9 30 42%
Docs/CI 11 14.8 24 20%

Takeaway: security stories (permissions, sandboxing, signed links, secrets) are 16% of the stories but about a quarter of supervision. Agents are close to "free" on normal and docs work (supervision about 20-25% of human effort) and barely help on security and unofficial external APIs. That is why those stories are human-led in the project.

The model

Every story has a three-point estimate in ideal days (optimistic O, most likely M, pessimistic P), a size (XS ≤ 0.5 d, S ≤ 1 d, M ≤ 3 d, L ≤ 5 d) and a risk class.

Human effort - Expected days E = (O + 4M + P) / 6, spread σ = (P − O) / 6. - Person-days = ΣE × (1 + overhead) × (1 + integration buffer); overhead 0.20 / 0.30 / 0.45 (review, tests, docs), buffer 0.10 / 0.15 / 0.25. - Calendar = person-days / (developers × focus factor); focus 0.75 / 0.65 / 0.55.

AI-agent effort (per story) - First-pass success p (a mergeable PR without human code changes) by size: XS 0.95 / 0.85 / 0.70, S 0.85 / 0.70 / 0.50, M 0.70 / 0.50 / 0.30, L 0.50 / 0.30 / 0.15, times a risk multiplier: docs 1.15, normal 1.0, core contract 0.8, integration 0.6, design/prompt 0.55, security 0.5, external API 0.5. - Up to 3 attempts; retries succeed more often (p + 0.2, max 0.9). Expected attempts A = 1 + (1−p) + (1−p)(1−p_retry). If all fail, a human takes over at 0.6 × the human effort (reusing partial work). - Agent wall-clock per attempt: XS 0.25 h, S 0.75 h, M 2 h, L 5 h. - Supervision per story = spec (XS 0.25 h … L 2 h, ×2 for security and design, ×1.5 for integration and external APIs) + A × review (max(0.25 h, 0.15 × E × 8 h), ×2 security, ×1.5 integration/external) + takeover; security stories add 0.25 × E for the human design; external-API stories add 2 h of manual testing with real accounts. - Plus fixed human work (architecture, releases, final security review) of 0.15 × ΣE, and a hardening buffer of 0.25 for agent-written code. - Calendar = max(supervision ÷ supervisor hours per week, agent compute ÷ (4 agents × 50 h/week)). Supervision always dominates here.

Evidence behind the parameters (2025-2026)

Finding Number Source
METR time horizon (50% success), frontier models hours to ~half a day; 80% horizon about 10x shorter METR TH 1.1, limitations
Tests-passing agent PRs that maintainers would merge about half METR, Mar 2026
Experienced OSS developers with AI (RCT) 19% slower (2025); ~18% faster in the weak 2026 follow-up METR uplift update
Anthropic engineers +50% self-reported productivity; "70%+ of my work is review" Anthropic research
Telemetry across companies throughput up, review time 2-5x, more bugs per developer Faros AI, DORA 2025
AI-co-authored PRs 1.7x issues; security issues 1.57x CodeRabbit
AI-written code with security flaws 45% of samples Veracode
Agent PR acceptance 50-80% depending on agent and task type; docs 82%, features 66% AIDev
Net gain after rework 15-20% overall; greenfield simple 30-40%; complex brownfield 0-10% Stanford talk

Caveats. No validated method exists to convert human estimates into agent effort; the AI parameters are a synthesis of the evidence above, deliberately wide. Benchmarks overstate real-world autonomy; vendor reports may overstate gains. Models change every few months: recalibrate p, review ratio and takeover rate from the project's own data (log spec time, review minutes, iterations and takeovers per story; Graft records most of it).

Assumptions to confirm

  • Supervisor time: 15 h/week (evenings and weekends). Change it and dates move proportionally.
  • 4 agents in parallel, each up to 10 h of work per day when stories are ready.
  • Human team: 3 experienced Python developers, full time.